3. The pressure regulator, condensate tank, valves and other equipment of PE pipes do not need to participate in the blowing process. These can only be installed after the blowing process is completed and qualified.
4. The blowing port should be located in a relatively open area and some reinforcement measures should be taken. Remember that the exhaust port needs to be grounded. When blowing the PE pipe, a safe area should be set up and no one is allowed to stand at the blowing outlet.
5. The pressure of the gas blown out should not exceed 0.3MPa.
The above introduces some steps when blowing PE pipes. It should be noted that this process of blowing PE pipes needs to be carried out multiple times. If you encounter any problems during the blowing process of PE pipes, you can consult us.